Timeline
~3 months · 6 phases · 13 planned weeks · hatched bars = risk windows
Phase / Epic
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
P0
Foundation
W1–1
E0.1
Foundation scaffold
P1
Contract pinning
W2–2
E1.1
Capture, Zod, golden master
P2
Mobile API parity
W3–7
E2.1
Catalog & pricing reads
E2.2
Customer-scoped reads
E2.3
Profile & address writes
E2.4
Auth & onboarding
E2.5
Orders — the crown jewels
E2.6
Payments
E2.7
Misc mobile
P3
Driver + realtime
W8–8
E3.1
Driver endpoints
E3.2
WebSocket gateway
P4
Admin + B2B + Routing
W9–12
E4.1
Admin panel (AccountController)
E4.2
Orders tracking + ops
E4.3
B2B (CompaniesController)
E4.4
Routing (RoutificController)
E4.5
Stored-procedure rewrites
P5
Cutover
W13–13
E5.1
Background jobs migration
E5.2
Cutover & decommission
Parallel tracks
Creds rotation
SP inventory
Q1 / Q4 / Q5 follow-ups